Fukushima Experimental Offshore Floating Wind Farm Project Second Phase Update
December 22, 2014     Japanese 
  JCN 
	  Network - Home
JCN Newswire
  Home  |  Companies  | Annual Reports  |  CSR  | News Alerts     
 
Fukushima Experimental Offshore Floating Wind Farm Project Second Phase Update - JCN Newswire
Share:
Fukushima Experimental Offshore Floating Wind Farm Project Second Phase Update

 Fukushima Offshore Wind Farm consortium
Tokyo, June 11, 2014 - (JCN Newswire) - A consortium made up of Marubeni (project integrator), the University of Tokyo (technical advisor), Mitsubishi, Mitsubishi Heavy Industries, Japan Marine United, Mitsui Engineering & Shipbuilding, Nippon Steel & Sumitomo Metal Corporation, Hitachi, Furukawa Electric, Shimizu, and Mizuho Information & Research has been participating in an experimental offshore floating wind farm project sponsored by the Ministry of Economy, Trade and Industry since March 2012. At present, the construction of the three-column semi-sub as part of the second phase has been successfully completed.

1. Outline of construction works in the second phase:

Setting one 7MW oil pressure drive-type floating wind turbine and undersea cables

2. Work progress to date:

< 7MW oil pressure drive-type floating wind turbine >
- Floater
Completion of construction of the three-column semi-sub floater and mooring it at Mitsubishi Heavy Industries, Ltd. Nagasaki Shipyard & Machinery Works.

- Wind Turbine
Parts procurement and construction of 7MW oil pressure drive-type floating wind turbine in progress at Mitsubishi Heavy Industries, Ltd. Yokohama Dockyard & Machinery Works.

< Undersea cables >
- Production of the undersea cable at Furukawa Electric Co., Ltd. Chiba Works.
- Preparation to connect cables to the 66kV floating power sub-station in progress.

3. Next Step

The following activities need to be completed to start operation of the power facilities during the current year:

- 7MW floating power facilities and undersea cable

Early June - late August: Laying chains and anchors at the testing area

Mid June - late August: Shipping, laying and burying the undersea cable at the testing area

From early December: Mounting wind turbine on three-column semi-sub at Onahama port

Note: Schedule will be changed depending on the meteorological and sea conditions

Please contact:

Mitsubishi Heavy Industries
Hideo Ikuno
h.ikuno@daiya-pr.co.jp
+81-3-6716-5277


June 11, 2014
From the Japan Corporate News Network
http://www.japancorp.net
Topic: Production report
View more news from these Sectors: Environment General, Energy General, Alternative Energy, Engineering


 